HS&E MAP practice question: Managing contractors and competence (4 of 4)

A. Legal and management A free question from our original HS&E MAP practice exam. Try it, then open the answer to see why each option is right or wrong.

Last verified against HSE guidance and the law ·How we write our questions

You are the principal contractor. The principal designer has information about hazards in the existing building.

What should happen?

Choose one answer.

  1. A. You liaise with the principal designer and share it
  2. B. You ignore it, as design is not your concern
  3. C. Only the client should see it, and it stays with them
  4. D. You wait for a problem before asking for it
Show the answer and explanation

Answer: A

  • A. Right: Right. HSE says the principal contractor must liaise with the principal designer and share relevant pre-construction information.
  • B. Wrong: Wrong. Hazard information affects how the work is done safely.
  • C. Wrong: Wrong. Information must reach the people doing the work.
  • D. Wrong: Wrong. Get the information before work starts.

Explanation

Principal contractors and principal designers must liaise and share pre-construction information.