A refurbishment and demolition survey is booked for part of a building.

What must happen in that area during the survey?

Choose one answer.

  1. A. Only office staff need to leave
  2. B. Windows must be shut, and people can stay
  3. C. The area must be vacated
  4. D. Normal work can carry on next to the surveyor
Show the answer and explanation

Answer: C

  • A. Wrong: Wrong. Everyone must leave the area.
  • B. Wrong: Wrong. The area must be vacated.
  • C. Right: Right. HSE says the survey involves destructive inspection, so the area must be vacated during it.
  • D. Wrong: Wrong. Destructive inspection can release fibres. The area must be empty.

Explanation

Refurbishment and demolition surveys are destructive, so the area must be vacated while they are done.