A trench is to be dug near a road on your site.

What should the planning include about buried services?

Choose one answer.

  1. A. Nothing, as the excavator driver will feel any cables
  2. B. Digging fast to finish before anyone finds out
  3. C. Plans, then tracing and marking services
  4. D. Only the plans, as they show exactly where services are
Show the answer and explanation

Answer: C

  • A. Wrong: Wrong. A machine can easily cut a cable.
  • B. Wrong: Wrong. That is dangerous and could kill someone.
  • C. Right: Right. HSE says get plans, use a cable locator to trace and mark services, and use safe digging methods.
  • D. Wrong: Wrong. Plans only give an indication. Services must be traced on site.

Explanation

Plan, locate and dig safely: get plans, trace and mark services, then hand dig trial holes.

Study