B. Right: Right. HSE says temporary works are parts of a project needed to build the permanent works, such as props, shoring, excavation support, falsework and formwork.
C. Wrong: Wrong. That is permanent works.
D. Wrong: Wrong. That is part of the permanent works.
Explanation
Temporary works let the permanent works be built: props, shoring, excavation support, falsework, formwork and access scaffolds.
What does the person organising them need to coordinate?
Choose one answer.
AA. Nothing, as temporary works are removed at the end
BB. Only the paperwork for the client
CC. Design, checks, loading and removal
DD. Only the purchase of the equipment
Show the answer and explanation
Answer: C
A. Wrong: Wrong. Temporary works failures can cause collapses.
B. Wrong: Wrong. It is about managing the works safely.
C. Right: Right. HSE says the person organising temporary works needs to coordinate design, equipment, contractors, supervision, checking completion, authorisation to load and removal.
D. Wrong: Wrong. Buying equipment is one part. Design, checks and permission to load and remove matter too.
Explanation
Temporary works must be managed: design, selection, supervision, checking, permission to load, and removal.
Does the law require a person called a temporary works coordinator?
Choose one answer.
AA. Only if HSE asks for one
BB. No, but they must still be managed
CC. Yes, on every project by law
DD. No, and temporary works don't need managing
Show the answer and explanation
Answer: B
A. Wrong: Wrong. Management is always needed, whoever does it.
B. Right: Right. HSE says there is no legal requirement to use that job title or the BS 5975 process, but temporary works must still be properly managed.
C. Wrong: Wrong. The title is not a legal requirement.
D. Wrong: Wrong. They must always be managed safely.
Explanation
A temporary works coordinator is good practice under BS 5975, not a legal title, but temporary works must always be managed.