Your gang has plans showing where the buried cables are on a site.

How far can you rely on the plans?

Choose one answer.

  1. A. Only as a guide; cables still need tracing on site
  2. B. Completely, as they show exactly where every cable is
  3. C. Not at all, so there is no point getting them
  4. D. Only if the plans are less than a year old
Show the answer and explanation

Answer: A

  • A. Right: Right. HSE says plans give only an indication of where services are. Cables must be traced with a locator and marked before digging.
  • B. Wrong: Wrong. Plans can be wrong or out of date, and cables move.
  • C. Wrong: Wrong. Plans are a useful starting point. They just need checking on site.
  • D. Wrong: Wrong. Even new plans only show roughly where services are.

Explanation

Service plans only show roughly where cables are. Trace and mark them with a locator, then confirm with hand-dug trial holes.