Welfare facilities on site questions for the CSCS test
7 free questions on Welfare facilities on site, from section B. Occupational health. Every question is original and explains why each option is right or wrong.
A small housing site is setting up its welfare cabin.
Which two must be provided for the workers? (Choose two.)
Choose two answers.
AA. Showers for everyone, whatever work they do on site
BB. Washbasins with warm water, soap and towels
CC. A place where workers can eat, drink and rest
DD. A canteen that serves cooked hot meals at lunchtime
Show the answer and explanation
Answers: B, C
A. Wrong: Wrong. Showers are needed where the work is particularly dirty, such as some demolition work, not on every site.
B. Right: Right. Washing facilities must have running hot and cold, or warm, water, soap and towels or dryers, next to the toilets.
C. Right: Right. There should be a room where workers can sit, eat and drink, and somewhere to store and dry clothing.
D. Wrong: Wrong. Workers need somewhere to eat and a way to boil water or heat food, not a canteen with cooked meals.
Explanation
Every site needs toilets, washbasins with hot and cold or warm water, soap and towels, a place to rest, eat and drink, and somewhere to store and dry clothing.
A large housing site has a principal contractor and many subcontractors.
Who must make sure welfare facilities are in place for the whole job?
Choose one answer.
AA. The principal contractor
BB. Each worker, by bringing their own
CC. The local council
DD. Nobody until the site has more than 50 workers
Show the answer and explanation
Answer: A
A. Right: Right. HSE says principal contractors must make sure welfare is provided from the start of the project until it finishes.
B. Wrong: Wrong. Welfare must be provided for workers, not by them.
C. Wrong: Wrong. The council doesn't provide welfare on construction sites.
D. Wrong: Wrong. Everyone on site needs welfare facilities, however many people are working.
Explanation
Everyone on site must have access to toilets, washing, changing, eating and rest facilities. The principal contractor makes sure they are there for the whole job.
DD. Flushing toilets connected to mains water and drainage
Show the answer and explanation
Answer: D
A. Wrong: Wrong. HSE says chemical toilets should only be used where other options aren't possible.
B. Wrong: Wrong. The site must provide its own toilets.
C. Wrong: Wrong. Toilets must be provided however long the job lasts.
D. Right: Right. HSE says flushing toilets connected to mains water and drainage are expected where possible. Portable chemical toilets are a last resort.
Explanation
Use mains-connected flushing toilets where possible. Chemical toilets are a last resort, and all toilets must be kept clean.