A demolition plan uses a top-down method on a building near other properties.
What does HSE say top-down demolition gives?
Choose one answer.
A A. A way to avoid any written methodB B. Permission to skip the asbestos surveyC C. Greater control over stability and debrisD D. A faster job with no need for exclusion zonesShow the answer and explanation Answer: C
A. Wrong: Wrong. Every method must be written down.B. Wrong: Wrong. The survey is still needed.C. Right: Right. HSE says top-down demolition gives greater control over stability and debris.D. Wrong: Wrong. Exclusion zones are still needed.Explanation Top-down demolition gives greater control over stability and debris, but still needs planning and exclusion zones.