You are planning the order in which parts of a structure will be removed.

What does HSE say the sequence must do?

Choose one answer.

  1. A. Leave the order to each worker
  2. B. Rule out any uncontrolled collapse
  3. C. Remove the main supports first, to save time
  4. D. Start wherever is easiest for the machine
Show the answer and explanation

Answer: B

  • A. Wrong: Wrong. The sequence is planned and written down.
  • B. Right: Right. HSE says use a sequence that eliminates the possibility of an uncontrolled collapse, removing non-critical elements first.
  • C. Wrong: Wrong. Removing supports early can cause collapse.
  • D. Wrong: Wrong. The sequence must keep the structure stable.

Explanation

Plan the sequence so there is no uncontrolled collapse, removing non-critical parts first.