Your workshop has welding LEV.

How often must it be thoroughly examined and tested?

Choose one answer.

  1. A. Never, if it still sucks
  2. B. At least every 14 months
  3. C. Every 5 years, or when it gets noisy
  4. D. Only when it is first installed
Show the answer and explanation

Answer: B

  • A. Wrong: Wrong. It must be at least every 14 months.
  • B. Right: Right. HSE says you must thoroughly examine and test LEV at least every 14 months.
  • C. Wrong: Wrong. It must be at least every 14 months.
  • D. Wrong: Wrong. It must be examined regularly.

Explanation

Thoroughly examine and test LEV at least every 14 months.