HS&E MAP practice question: CDM 2015 duties (2 of 4)

A. Legal and management A free question from our original HS&E MAP practice exam. Try it, then open the answer to see why each option is right or wrong.

Last verified against HSE guidance and the law ·How we write our questions

You are the principal contractor on a project with several contractors.

When must the construction phase plan be ready?

Choose one answer.

  1. A. Before the construction phase begins
  2. B. Within a month of starting work on site
  3. C. At the end of the project, for the health and safety file
  4. D. Only if HSE asks for one
Show the answer and explanation

Answer: A

  • A. Right: Right. HSE says the principal contractor must prepare a written construction phase plan before the construction phase begins, then keep it under review.
  • B. Wrong: Wrong. The plan must be in place before work starts.
  • C. Wrong: Wrong. The plan is for managing the work. The health and safety file is a different document.
  • D. Wrong: Wrong. It is required whether or not HSE asks.

Explanation

The construction phase plan must be ready before the construction phase starts, and reviewed as the work goes on.