HS&E MAP practice question: CDM 2015 duties (3 of 4)
A. Legal and management A free question from our original HS&E MAP practice exam. Try it, then open the answer to see why each option is right or wrong.
A client is planning a project with several contractors.
Who must the client appoint to control the construction phase?
Choose one answer.
AA. The cheapest of the contractors, with no formal role
BB. An HSE inspector
CC. Nobody, as each contractor manages itself
DD. A principal contractor
Show the answer and explanation
Answer: D
A. Wrong: Wrong. A principal contractor must be appointed, and they must have the skills and capability for the role.
B. Wrong: Wrong. HSE enforces the law. It doesn't run projects.
C. Wrong: Wrong. Someone must plan, manage and coordinate the whole construction phase.
D. Right: Right. HSE says the client appoints a principal contractor to control the construction phase of any project with more than one contractor.
Explanation
On projects with more than one contractor, the client appoints a principal contractor for the construction phase and a principal designer for the pre-construction phase.