You are reviewing a plan for demolishing a warehouse.

What must the plan prevent?

Choose one answer.

  1. A. Dust from reaching the demolition workers only
  2. B. The job taking longer than the agreed programme
  3. C. Noise from the machines affecting the client's staff
  4. D. Any uncontrolled collapse of the structure
Show the answer and explanation

Answer: D

  • A. Wrong: Wrong. Dust control matters, but the key is to prevent uncontrolled collapse.
  • B. Wrong: Wrong. Safety comes before the programme.
  • C. Wrong: Wrong. Noise matters, but the plan must above all prevent uncontrolled collapse.
  • D. Right: Right. HSE says demolition must be planned and carried out to prevent danger, and avoid uncontrolled collapse.

Explanation

Demolition must be planned in writing by a competent person to prevent uncontrolled collapse.