A wall is to be removed to make an opening in an existing building.

Who should decide the method and design of temporary supports?

Choose one answer.

  1. A. A competent person, after a survey
  2. B. The newest labourer on site
  3. C. Whoever has the biggest hammer
  4. D. Nobody, as the wall can just be knocked out
Show the answer and explanation

Answer: A

  • A. Right: Right. HSE says a competent person should survey and assess the structure and decide the method and the design of temporary supports.
  • B. Wrong: Wrong. This needs a competent person.
  • C. Wrong: Wrong. This needs planning and design.
  • D. Wrong: Wrong. That could cause a collapse.

Explanation

Alterations need a structural survey and a competent person to plan the method and temporary supports.