There were very strong winds overnight. The scaffold you are working on was last inspected three days ago.
What should happen before anyone uses it?
Choose one answer.
AA. The first person up should give it a shake to check it
BB. Use it, but only on the lower lifts
CC. A competent person must inspect it again
DD. Nothing, as the next inspection isn't due for four days
Show the answer and explanation
Answer: C
A. Wrong: Wrong. The inspection must be done properly by a competent person, not by a quick check from a user.
B. Wrong: Wrong. Wind damage could affect any part of the scaffold, including the ties and base.
C. Right: Right. A scaffold must be inspected before first use, at least every 7 days, and after anything that could affect its safety, such as high winds.
D. Wrong: Wrong. The 7-day inspection is the longest gap allowed. Events such as high winds mean it needs checking again first.
Explanation
Scaffolds are inspected by a competent person before first use, at least every 7 days, and after anything that could affect them, such as strong winds.