A contractor is planning to demolish a three-storey building.

What does HSE say about the demolition method?

Choose one answer.

  1. A. It only needs to be agreed by the neighbours
  2. B. There is no need for a method on small buildings
  3. C. It must be written down by a competent person
  4. D. It can be decided by the machine driver on the day
Show the answer and explanation

Answer: C

  • A. Wrong: Wrong. Neighbours may need informing, but the method must be planned by a competent person.
  • B. Wrong: Wrong. All demolition needs a planned method.
  • C. Right: Right. HSE says the demolition method must be written by a competent person, and planned so there can be no uncontrolled collapse.
  • D. Wrong: Wrong. Demolition must be planned in advance by a competent person.

Explanation

Demolition must be planned and written down by a competent person, so the structure comes down in a controlled way.

Study