You are planning the demolition of a four-storey office block.
Who must write the demolition method?
Choose one answer.
A A. Nobody, as experienced gangs don't need a written methodB B. A competent personC C. The first machine driver to arrive on site that morningD D. The client's office manager, who knows the building bestShow the answer and explanation Answer: B
A. Wrong: Wrong. The method must be written down.B. Right: Right. HSE says the demolition method must be written by a competent person and account for all hazards and risks.C. Wrong: Wrong. The method must be planned and written before work starts.D. Wrong: Wrong. Knowing the building isn't the same as being competent to plan its demolition.Explanation Demolition must be planned, and the method written by a competent person, before the work begins.