E. Specialist: Demolition A free question from our original HS&E DEM practice exam. Try it, then open the answer to see why each option is right or wrong.

Last verified against HSE guidance and the law ·How we write our questions

The demolition method for a job has been written.

What must happen to it?

Choose one answer.

  1. A. It is only shown to the client, who signs it off
  2. B. It is thrown away once work starts
  3. C. It goes in the plan of work and the team is told
  4. D. It is kept in the director's office in case HSE asks
Show the answer and explanation

Answer: C

  • A. Wrong: Wrong. It must be communicated to the whole contract team.
  • B. Wrong: Wrong. The team works to it throughout.
  • C. Right: Right. HSE says the method must be fully documented in the plan of work and communicated to the contract team.
  • D. Wrong: Wrong. The people doing the work need to know the method.

Explanation

Write the demolition method into the plan of work and make sure the whole team knows it.