A client is about to award a demolition contract for a complex structure.
What does HSE advise the client to do first?
Choose one answer.
A A. Choose the cheapest price and leave the rest to the contractorB B. Ask the neighbours which contractor they likeC C. Nothing, as clients have no duties for demolitionD D. Get advice from a competent demolition engineerShow the answer and explanation Answer: D
A. Wrong: Wrong. Clients should take competent advice and appoint people with the right skills.B. Wrong: Wrong. Choose on competence, with engineering advice.C. Wrong: Wrong. Clients have duties, including appointing competent contractors.D. Right: Right. HSE says clients should get advice from a competent demolition engineer before awarding a contract.Explanation Clients should take advice from a competent demolition engineer and appoint contractors with the right skills.