Temporary props are needed while an opening is formed in a load-bearing wall.
Who should design them?
Choose one answer.
A A. Whoever has spare props in their vanB B. The labourer who will fit themC C. Nobody, as one prop per metre is always enoughD D. Experienced temporary works designersShow the answer and explanation Answer: D
A. Wrong: Wrong. Props must be designed for the loads.B. Wrong: Wrong. The design needs temporary works experience.C. Wrong: Wrong. There is no rule of thumb; they must be designed.D. Right: Right. HSE says all bracing and propping should be designed by experienced temporary works designers.Explanation Temporary bracing and propping must be designed by experienced temporary works designers.