HS&E DEM practice question: Structural stability and temporary support (4 of 6)
E. Specialist: Demolition A free question from our original HS&E DEM practice exam. Try it, then open the answer to see why each option is right or wrong.
Props have been designed for a partly demolished building.
How must they be installed and removed?
Choose one answer.
AA. In line with the designer's specification
BB. However the gang thinks best on the day
CC. Removed as soon as they get in the way
DD. Left in place for good, so nothing can move
Show the answer and explanation
Answer: A
A. Right: Right. HSE says temporary support must be installed, checked, inspected, maintained and dismantled in accordance with the designer's specification.
B. Wrong: Wrong. They must follow the design.
C. Wrong: Wrong. Removing props early can cause collapse.
D. Wrong: Wrong. They are removed in a controlled way, to the design.
Explanation
Install, check, maintain and remove temporary supports exactly as the designer specifies.