Props have been designed for a partly demolished building.

How must they be installed and removed?

Choose one answer.

  1. A. In line with the designer's specification
  2. B. However the gang thinks best on the day
  3. C. Removed as soon as they get in the way
  4. D. Left in place for good, so nothing can move
Show the answer and explanation

Answer: A

  • A. Right: Right. HSE says temporary support must be installed, checked, inspected, maintained and dismantled in accordance with the designer's specification.
  • B. Wrong: Wrong. They must follow the design.
  • C. Wrong: Wrong. Removing props early can cause collapse.
  • D. Wrong: Wrong. They are removed in a controlled way, to the design.

Explanation

Install, check, maintain and remove temporary supports exactly as the designer specifies.