E. Specialist: Demolition A free question from our original HS&E DEM practice exam. Try it, then open the answer to see why each option is right or wrong.

Last verified against HSE guidance and the law ·How we write our questions

A site is too small for the exclusion zone that the planned demolition method needs.

What does HSE say to do?

Choose one answer.

  1. A. Choose a different technique
  2. B. Make the zone smaller and carry on
  3. C. Put up a sign asking people to keep clear
  4. D. Do the demolition at night
Show the answer and explanation

Answer: A

  • A. Right: Right. HSE says debris must stay within the exclusion zone if a collapse occurs. Where space is limited, choose a different technique.
  • B. Wrong: Wrong. A smaller zone may not contain the debris.
  • C. Wrong: Wrong. A sign won't stop falling debris.
  • D. Wrong: Wrong. Timing doesn't make the zone big enough.

Explanation

If the site is too small for the exclusion zone a method needs, use a different method.