You are reviewing a demolition plan.
What must the plan show?
Choose one answer.
A A. Only where the skips will goB B. Only the site cabin layoutC C. Only the client's parking spaces and the site entranceD D. The safe working zones, exclusion zones and debris zonesShow the answer and explanation Answer: D
A. Wrong: Wrong. Zones that keep people safe must be shown too.B. Wrong: Wrong. The plan must show the safety zones.C. Wrong: Wrong. The plan must show exclusion and debris zones.D. Right: Right. HSE says plans should show where the planned safe working zones, exclusion zones and debris zones are.Explanation Demolition plans show safe working zones, exclusion zones and debris zones.
Study A site is too small for the exclusion zone that the planned demolition method needs.
What does HSE say to do?
Choose one answer.
A A. Choose a different techniqueB B. Make the zone smaller and carry onC C. Put up a sign asking people to keep clearD D. Do the demolition at nightShow the answer and explanation Answer: A
A. Right: Right. HSE says debris must stay within the exclusion zone if a collapse occurs. Where space is limited, choose a different technique.B. Wrong: Wrong. A smaller zone may not contain the debris.C. Wrong: Wrong. A sign won't stop falling debris.D. Wrong: Wrong. Timing doesn't make the zone big enough.Explanation If the site is too small for the exclusion zone a method needs, use a different method.
Study A demolition site is next to a busy shopping street.
What should the plan make sure of if part of the building collapses?
Choose one answer.
A A. The shops close for an hourB B. Debris stays inside the siteC C. Shoppers are told to walk fasterD D. The street is swept clean once the work is finishedShow the answer and explanation Answer: B
A. Wrong: Wrong. The plan must contain debris whatever happens.B. Right: Right. HSE says plan the work so debris remains within a defined area, and a collapse can't breach the site boundary.C. Wrong: Wrong. The plan must keep debris inside the site.D. Wrong: Wrong. Debris must not reach the street at all.Explanation Plan demolition so debris from a planned or accidental collapse can't leave the site.
Study Dust is drifting from your demolition site onto nearby homes.
What does HSE say?
Choose one answer.
A A. Only work when it is windy so the dust blows awayB B. Ask the neighbours to keep their windows shut, and carry onC C. Limit the escape of dust and debrisD D. Dust doesn't matter outside the siteShow the answer and explanation Answer: C
A. Wrong: Wrong. Wind spreads dust further.B. Wrong: Wrong. Control the dust at source.C. Right: Right. HSE says you should limit the escape of dust and debris.D. Wrong: Wrong. Dust can harm neighbours and the public.Explanation Limit the escape of dust and debris, for example by damping down and using screens.
Study A demolition site is in a confined space between other businesses.
What must the plan address?
Choose one answer.
A A. Only the contractor's own staffB B. Nothing extra, as small sites are lower riskC C. Only the start and finish dates for the neighboursD D. Protecting neighbours from collapseShow the answer and explanation Answer: D
A. Wrong: Wrong. Neighbours and the public must be protected too.B. Wrong: Wrong. Confined sites can make collapse more dangerous for neighbours.C. Wrong: Wrong. Safety must be planned.D. Right: Right. HSE says protect nearby people and businesses, and address the collapse risk where the site is confined.Explanation On confined sites, plan to protect neighbours and the public from collapse and debris.
Study A demolition plan uses one exclusion zone size for every method on the job.
What is wrong with this?
Choose one answer.
A A. Zone size depends on the methodB B. Nothing, as one size suits all methodsC C. Zones are only needed for explosivesD D. Zones should always be exactly 5 metresShow the answer and explanation Answer: A
A. Right: Right. HSE says exclusion and debris zones depend on the demolition technique.B. Wrong: Wrong. Different methods throw debris different distances.C. Wrong: Wrong. Every demolition method needs exclusion zones.D. Wrong: Wrong. There is no fixed size.Explanation Size each exclusion zone for the method being used.