A demolition site is in a confined space between other businesses.
What must the plan address?
Choose one answer.
A A. Only the contractor's own staffB B. Nothing extra, as small sites are lower riskC C. Only the start and finish dates for the neighboursD D. Protecting neighbours from collapseShow the answer and explanation Answer: D
A. Wrong: Wrong. Neighbours and the public must be protected too.B. Wrong: Wrong. Confined sites can make collapse more dangerous for neighbours.C. Wrong: Wrong. Safety must be planned.D. Right: Right. HSE says protect nearby people and businesses, and address the collapse risk where the site is confined.Explanation On confined sites, plan to protect neighbours and the public from collapse and debris.