The locator shows a cable running across your trench line. You are hand digging to expose it.
How should you dig?
Choose one answer.
A A. With a pick, to break through quicklyB B. By probing the ground with a long metal barC C. Alongside the cable, not on top of itD D. Straight down onto it to find it fastShow the answer and explanation Answer: C
A. Wrong: Wrong. A pick can pierce a cable.B. Wrong: Wrong. A metal bar could pierce a live cable.C. Right: Right. HSE says excavate alongside the service rather than directly above it, using insulated tools near electric cables.D. Wrong: Wrong. You could strike the cable.Explanation When exposing a cable, dig alongside it, not directly above, and use insulated tools.