Excavations in the highway questions for the Highway works (HIW) specialist test
6 free questions on Excavations in the highway, from section E. Specialist: Highway works. Every question is original and explains why each option is right or wrong.
Spoil from a trench is piled right next to its edge, where people are working below.
What does HSE say?
Choose one answer.
AA. Pile it higher so it takes up less room
BB. Nothing, as spoil can't roll back in
CC. Wet it down so that it sticks together and stays put
DD. Stop it falling in, for example with toe boards
Show the answer and explanation
Answer: D
A. Wrong: Wrong. A higher pile adds weight and more can fall in.
B. Wrong: Wrong. Loose material can fall into the trench.
C. Wrong: Wrong. Wet spoil is heavier and can still slip.
D. Right: Right. HSE says loose material can fall from spoil heaps into the excavation. Toe boards or projecting trench sheets can stop it, and head protection should be worn.
Explanation
Keep spoil and materials back from the edge and stop them falling in, with toe boards or raised trench sheets.
A trench next to a busy footway will be left open overnight.
What should you do?
Choose one answer.
AA. Leave a ladder in it so people can climb out
BB. Cover it, or put strong barriers round it
CC. Leave a cone at each end
DD. Put tape across the top
Show the answer and explanation
Answer: B
A. Wrong: Wrong. HSE says remove access ladders, so children can't climb in.
B. Right: Right. HSE says protect excavation edges with substantial barriers and remove access ladders. The street works code says consider temporary covers or enhanced barriers.
C. Wrong: Wrong. Cones won't stop someone falling in.
D. Wrong: Wrong. Tape won't stop a fall.
Explanation
Guard open excavations near the public with covers or substantial barriers, and take ladders out.